Financed ProjectsPulkovo Airport
Identification Code:
OP/09/0746
Total Operation Cost:
1.193.000.000
Maturity:
180 months
Operation Status:
BSTDB Approved Amount
15.000.000 EUR
15.000.000 EUR
Approval Date
16 Apr 2010
16 Apr 2010
BSTDB Signed Amount
15.000.000 EUR
15.000.000 EUR
Signed Date
28 Apr 2010
28 Apr 2010
Status:
Completed
Description and Purpose of the Operation:
A project finance loan with proceeds earmarked for financing of costs related to expansion, operation and maintenance of Pulkovo Airport in St. Petersburg, Russia. The Operation is the first Russian PPP (public-private partnership) project.
Countries of Operation:
Russia (100,00 %)
Financial Product:
Loans
Sector:
Industrials
Domain:
Private
Borrower/Client:
The Northern Capital Gateway LLC is a limited liability company representing the winning consortium "Northern Gateway consortium" for the construction, operation and maintenance of the Pulkovo Airport.
Co-Financiers/Participants:
EBRD, IFC, Vnesheconombank, Eurasian Development Bank, Nordic Investment Bank, other Commercial Banks and Equity
Guarantors/Sponsors:
The shareholders of Northern Capital Gateway LLC
Developmental and Regional Cooperation Impact:
The Operation will have a strong developmental impact and will result in: - Construction of the auxiliary facilities (hotels, car parks); - Improvement of reliability of traffic in St. Petersburg region and adjacent areas serviced by Pulkovo hub; - Construction of a new Terminal building which will serve both domestic and international passengers; - New jobs creation in St. Petersburg and the city’s adjacent areas; - Mobilization of capital and transfer of advanced technologies due to participation of the foreign consortium members.
Environmental Classification and Impact (summary):
Screened as category B1. Environmental Assessment process identified the following key issues as being relevant to the Project: i) environmental and social management systems; ii) occupational health and safety management; iii) ambient air quality and air emissions; iv) treatment and discharge of wastewater and run-off water; v) solid waste management; vi) subsurface past pollution; vii) noise pollution; viii) fuel and hazardous materials storage and handling; ix) emergency response planning; and x) community health and safety, and consultation. All these issues have been addressed in the Company's Environmental and Social Action Plan which will be implemented during the course of the project and which will significantly increase the general EH&S performance of Pulkovo Airport.
Operation Leader:
General Industries, Transport, Tourism 1
E-mail:
gitt1@bstdb.org